Designed to address the healthcare emergency highlighted by WHO indicators, this PPP project aims to provide Douala and Bertoua with modern outpatient care centres; its implementation remains conditional on securing the project sites.
Accelerating growth and mobilizing, through a public-private partnership, the capital and expertise required to modernize public healthcare services is the ambition behind the Outpatient Care Hospital Centres project. It responds to a concerning situation highlighted by the WHO: Cameroon remains one of the countries where the infant mortality rate, at 122 deaths per 1,000 live births, has declined the least, while maternal mortality has increased significantly, from 432 deaths per 100,000 live births in 2010 to 670 in 2017, and then 778 in 2024.
Against this backdrop, and despite the high level of training among Cameroonian healthcare professionals, the existing healthcare supply does not sufficiently meet the population’s growing needs in light of WHO standards. The project introduces a new model: the Outpatient Care Hospital Centre, where patients receive comprehensive care — including general medicine, ophthalmology, paediatrics, digestive diseases, trauma care and maternity services — without hospitalization exceeding 24 hours. This model could cover up to 90% of maternity needs, 95% of paediatric needs excluding neonatology, 80% of surgical needs and 70% of general medical needs normally handled in conventional hospital settings.
The project provides for the financing, construction, operation and maintenance of these centres in Douala and Bertoua, with deployment in three stages: a diagnostic unit and its extension, standardized intervention units, and finally a maternity unit.
However, implementation has experienced a significant delay, mainly due to a change of site in Douala. While a 4-hectare site was initially expected to be provided by the Douala City Council, the Ministry of State Property, Surveys and Land Tenure (MINDCAF) identified an alternative 23.7-hectare site in Bonamoussadi, which is currently contested. This has delayed the launch of the soil studies required to finalize the hospital designs. In Bertoua, by contrast, a 2-hectare site was made available by the Mayor in the Koumé area and has been subject to a declaration of public utility. The programme studies for both hospitals have already been completed.
Once the Douala site has been secured, soil studies and detailed design studies can be launched simultaneously in both cities. The project’s pilot phase will be implemented in Douala in order to give the initiative greater national visibility.
| Beneficiaries | Cities of Douala and Bertoua |
| Identified Sites | 23.7 ha in Bonamoussadi (Douala, contested) — 2 ha in Koumé (Bertoua, secured) |
| Private Partner’s Responsibilities | Finance, construct, operate, maintain |
| Deployment Phases | Diagnostic unit → standardized intervention units → maternity unit |
| Project Status | Delay due to securing the Douala site; programme studies completed |