Led by the Ministry of Housing and Urban Development (MINHDU) and private partner AMCA, this large-scale social housing programme is awaiting the fulfilment of two conditions precedent before fully entering into force, under an amendment that has been under development since 2024.
On September 17, 2013, the State of Cameroon, represented by the then Minister of Housing and Urban Development, Ms. Célestine Keutcha Courtes, signed a public-private partnership agreement with AMCA, represented by its Managing Director, Mr. Omboui André, for the construction of 5,000 social housing units in Yaoundé. The project encompasses not only the housing units themselves, but also access infrastructure, roads and utility networks, as well as a range of community facilities, including schools, hospitals, commercial areas, places of worship, sports and leisure facilities, cemeteries and security services.
The private partner is responsible for financing, designing, constructing and marketing the housing units, as well as maintaining unsold units in order to preserve their original condition. The access infrastructure, roads and utility networks, and community facilities will also be delivered by the private partner, but financed by the public partner, in accordance with the contractual schedule. The overall project cost is estimated at CFA 121.1 billion including taxes.
As revised by the amendment currently being finalized, the contract is concluded for a period of 8 years from its entry into force: 3 years dedicated to construction, until full completion of the housing units, followed by 5 years dedicated to marketing, starting from the handover of the first housing unit sold. The two phases may overlap.
In 2024, MINHDU and the Prime Minister’s Office initiated an amendment setting out the terms and conditions for the implementation of the contract. Its entry into force remains on hold, however, pending the fulfilment of two conditions precedent: the effective handover of the land to the private partner, as documented by official minutes, and the submission by the private partner of proof that the equity required to carry out the project’s studies is available. The signing of official minutes confirming the fulfilment of these conditions will mark the effective entry into force of the contract and its amendment.
This project illustrates the challenges inherent in large-scale social housing programmes: beyond financing and technical design, securing the land upstream remains a decisive step in enabling the effective start of construction works.
| Beneficiary | City of Yaoundé |
| Public Partner | MINHDU |
| Private Partner | AMCA |
| Total Project Cost | CFA 121.1 billion incl. tax |
| Contract Duration | 8 years (3 years construction + 5 years marketing) |
| Initial Signature / Amendment | September 17, 2013 — amendment under development since 2024 |
| Project Status | Entry into force on hold (conditions precedent) |