The members of the Monitoring and Evaluation Committee for the CNPS Building Rehabilitation Project on Charles de Gaulle Avenue held their seventh session in the meeting room set up at the project site on Friday, 22 January 2021, to discuss issues relating to the amendment to Partnership Contract No. 02/17/DG/DFP/SIYA/BM/CNPS/2017. The Committee, chaired by the private partner FINANCIA PROPERTIES, comprises three representatives of the latter, three representatives of the CNPS (the public partner), and one representative of CARPA.
The meeting held on 22 January 2021 focused on project financing options other than the private partner’s equity, which currently constitutes the project’s sole source of funding. The members also examined a number of proposed changes that could lead to the signing of an amendment by the parties. In addition to financing, these changes could concern the project timeline and the scope of the works.
By way of reminder, the project involves the rehabilitation of the 15-storey CNPS building, located in the heart of Bonanjo in Douala. Built around the 1980s for use as modern rental housing, the building went without adequate maintenance for several years and consequently lost a significant portion of its market value, despite being located in an area of high economic value.
This economic value was the main reason behind the decision taken by the CNPS around 2013 to rehabilitate the building through a public procurement mechanism known as a partnership contract, with the ultimate aim of converting it into a very high-end hotel residence.
The selected private partner, FINANCIA PROPERTIES, a project company established by FINANCIA CAPITAL, the successful bidder for the contract, is responsible for financing, rehabilitating, converting, extending, operating and maintaining the building over a period of 22 years, including two years of construction works.
As of 22 January 2021, the works had reached a stage at which the foundations had been 100% reinforced with piles, the shear walls had been 95% reinforced, new balconies had been added to each floor, and the flooring of the restaurant and spa was nearly 90% complete, to mention only a few aspects of the work.